1. CPM requires ?

single time estimate

double time estimate

triple time estimate

none of these

Answer: none of these

Explanation:


2. The post-tender stage of construction consists of ?

assessment of work

finalisation of accounts

assessment of expenditure during execution

all of the above

Answer: all of the above

Explanation:


3. An Assistant Engineer may have powers upto rupees ?

twenty five thousand

one lakh

two lakh

two lakh

Answer: twenty five thousand

Explanation:


4. Which of the following statement is wrong ?

An activity consumes time and resources whereas an event do not

The performance of a specific task is called an activity

An event is an instantaneous point in time at which an activity begins or ends

none of the above

Answer: none of the above

Explanation:


5. Milestone chart is an improvement over ?

bar chart

PERT

CPM

all of these

Answer: bar chart

Explanation:


6. PERT requires ?

single time estimate

double time estimate

triple time estimate

none of these

Answer: triple time estimate

Explanation:


7. PERT ?

provides an approach for keeping planning up-to-date

provides a way for management to require that planning be done on a uniform and logical basis

permits management to foresee quickly the impact of variations from the plan

all of the above

Answer: all of the above

Explanation:


8. Bar chart is suitable for ?

large project

major work

minor work

all of these

Answer: minor work

Explanation:


9. The contractor is responsible for ?

procuring material which is not supplied by the owner

organising and planning the work as per drawing

executing the work as per specifications laid down in

all of the above

Answer: all of the above

Explanation:


10. A Gantt chart indicates ?

balance of work to be done

efficiency of project work

comparison of actual process with the scheduled progress

progress cost of project

Answer: comparison of actual process with the scheduled progress

Explanation: