1. The estimated time required to complete an activity is known as ?

duration

float

restraint

all of these

Answer: duration

Explanation:


2. The major principle of an organisation is ?

span of management

unity of command

delegation of authority

all of these

Answer: all of these

Explanation:


3. Technical planning is carried out for the ?

preparation of detailed drawings

preparation of detailed estimate

planning resources and initiating procurement action

all of the above

Answer: all of the above

Explanation:


4. Functional organisation system of working was introduced by ?

Henry Gantt

F.W. Taylor

M.R. Walker

none of these

Answer: F.W. Taylor

Explanation:


5. A critical activity has ?

maxitnum float

minimum float

zero float

average float

Answer: zero float

Explanation:


6. The early finish time of an activity is the ............ of early start time and duration of activity ?

sum

difference

product

ratio

Answer: sum

Explanation:


7. Which of the following are the guidelines for the construction of a network diagram ?

Each activity is represented by one and only arrow in the network

Dangling must be avoided in a network diagram

Dummy activity consumes no time or resource

all of the above

Answer: all of the above

Explanation:


8. The start or completion of task is called ?

an event

an activity

a duration

any one of these

Answer: an activity

Explanation:


9. The total activity slack is equal to ?

Late start time - Early start time

Late finish time – Early finish time

Latest allowable event occurrence time - Early finish time

all of the above

Answer: all of the above

Explanation:


10. A dummy activity in a net work ?

is represented by a dotted line

is an artificial activity

does not consume time or resources

all of these

Answer: all of these

Explanation: