1. The construction of ................ belongs to industrial construction ?

transit sheds

tunnels

dams

chemical plants

Answer: chemical plants

Explanation:


2. The main function of the construction management is ?

planning

organising

directing

all of these

Answer: all of these

Explanation:


3. The resources in a construction project are made up of ?

plant equipment and machinery required for the project

construction materials such as cement, bricks, steel etc

skilled and unskilled manpower

all of the above

Answer: all of the above

Explanation:


4. A bar chart is drawn for ?

time versus activity

activity versus resources

resources versus progress

progress versus time

Answer: time versus activity

Explanation:


5. Probabilistic time for completion of any activity can be found out from ?

optimistic time

pessimistic time

most likely time

all of these

Answer: all of these

Explanation:


6. The salient feature of the organisation evolved by F.W. Taylor is ?

strict adherence to specification

separation of planning and design part for field work

each individual maintains functional efficiency

all of the above

Answer: all of the above

Explanation:


7. The bar chart is also ?

flow chart

time chart

travel chart

Gantt chart

Answer: Gantt chart

Explanation:


8. Dummy activities are used to ?

determine the critical path

determine the project completion time

maintain the required net work

none of these

Answer: maintain the required net work

Explanation:


9. The amount of time by which the activity completion can te start of succeeding activity, is known as ?

earliest completion time

total float

free float

none of these

Answer: free float

Explanation:


10. Travel charts are used to ?

analyse material handling

determine inventory control difficulties

plan material handling procedure and routes

all of the above

Answer: all of the above

Explanation: