1. In jobbing production ?

highly skilled workers are needed

unit costs are high

operations are labour-intensive

all of these

Answer: all of these

Explanation:


2. The process capability of a machine is defined as the capability of the machine to ?

produce a definite volume of work per minute

perform definite number of operations

produce job at a definite spectrum of speed

hold a definite spectrum of tolerance and surface finish

Answer: produce a definite volume of work per minute

Explanation:


3. PERT is appued for ?

marketing programmes and advertising programmes

installation of machinery

research and development of products

all of these

Answer: all of these

Explanation:


4. Dispatching ?

prescribes the sequence of operations to be followed

determines the programme for the operations

is concerned with the starting of processes

regulates the progress of job through various processes

Answer: is concerned with the starting of processes

Explanation:


5. Time study is used to ?

determine standard costs

determine the number of machines a person may run

provide a basis for setting piece price or incentive wages

all of the above

Answer: all of the above

Explanation:


6. CPM requires ?

single time estimate

double time estimate

triple time estimate

none of these

Answer: single time estimate

Explanation:


7. At the break even point ?

total cost is more than the sales revenue

total cost is less than the sales revenue

total cost is equal to sales revenue

fixed cost is equal to variable

Answer: total cost is equal to sales revenue

Explanation:


8. The aim of value engineering is to ?

find the depreciation value of a machine

determine the selling price of a product

minimise the cost without change in quality of the product

all of the above

Answer: minimise the cost without change in quality of the product

Explanation:


9. Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved ?

Halsey plan

Gantt plan

Rowan plan

Emerson's efficiency plan

Answer: Halsey plan

Explanation:


10. Probabilistic time for completion of any activity can be found out from ?

optimistic time

pessimistic time

most likely time

all of these

Answer: all of these

Explanation: