1. A pitched roof in which rafters slope to one side only is called ?

lean-to roof

Pent roof

Aisle roof

any one of these

Answer: any one of these

Explanation:


2. Frog is defined as a ?

depression on the top face of a brick

topmost course of plinth

brick whose one end is cut splayed or mitred

brick used for the corner of a wall

Answer: depression on the top face of a brick

Explanation:


3. H-piles ?

require large storage space

are difficult to handle

cannot withstand large impact stress developed during hand driving

none of the above

Answer: none of the above

Explanation:


4. The minimum depth of foundation for the load bearing wall of a building is restricted to ?

600 mm

700 mm

800 mm

900 mm

Answer: 900 mm

Explanation:


5. Which of the following statement is wrong ?

The part of the wall on which the arch rests, is called abutment

Soffit is the under surface of an arch

Crown is the highest point of the intrados

all of the above

Answer: Crown is the highest point of the intrados

Explanation:


6. In a raking bond ?

all the bricks are laid as headers

all the bricks are laid as stretches

the arrangement of bricks is similar to English bond

the bonding bricks are laid at any angle other than zero or ninety degree

Answer: the bonding bricks are laid at any angle other than zero or ninety degree

Explanation:


7. The span of an arch is ?

vertical distance between the springing line and the highest point on the intrados

vertical distance between the springing line and the highest point on the extrados

perpendicular distance between the intrados and extrados

horizontal distance between the supports

Answer: horizontal distance between the supports

Explanation:


8. The angle which the line of nosing of the stair makes with the horizontal, is called ?

riser

flier

soffit

pitch or slope

Answer: pitch or slope

Explanation:


9. A type of cast-in-situ pile best suited for places where the ground is soft and offers little resistance to the flow of concrete, is ?

simplex pile

Franki pile

vibro-pile

Raymond pile

Answer: vibro-pile

Explanation:


10. The length of pre-cast concrete piles varies from ?

3 m to 4.5 m

4.5 m to 10 m

4.5 m to 20 m

4.5 m to 30 m

Answer: 4.5 m to 30 m

Explanation: